Performance % Complete reads 0% at the top of the WBS, and the schedule is far from empty. It carries 2,000 budgeted labour hours. Nobody has priced a single resource yet, and the client still wants one progress figure for the whole package. A planner asked almost exactly this on r/primavera this month, so here is an earned value analysis example done entirely in hours.
The short answer: report earned hours. Multiply each activity's baseline labour hours by its percent complete, add those earned hours up the WBS, and divide by the baseline hours at the same level. That gives you a properly weighted progress figure without a single cost on the schedule, and P6 already calculates most of it for you.
Why the top of the WBS shows zero
At activity level, Performance % Complete behaves. With the default earned value technique (activity percent complete) it simply follows each activity's own % complete.
The trouble starts when P6 summarises it. For a WBS node, Performance % Complete is earned value cost divided by budget at completion, and both of those are cost fields. No prices means no cost. No cost means there is nothing to divide, so the band sits at zero however much concrete has been poured.
This isn't a bug. Earned value in P6 was built around cost, and labour units are its second language. A fluent second language, though, which is the part most people miss.
Two numbers P6 will show you instead
Open the column list and there are two candidates that work without any cost at all. They answer different questions, and mixing them up is how a progress report ends up flattering a job that is going badly.
Units % Complete
Actual units divided by at completion units. It rolls up cleanly through the WBS bands and it fills in the moment anyone records hours. It is also measuring the wrong thing for a progress report. It tells you how much of the expected labour has been spent, not how much of the work exists on site. A crew that burns hours without producing anything pushes this number up.
Earned Value Labor Units
P6 takes Performance % Complete on each activity and multiplies it by the baseline's budgeted labour units. That is earned hours. It sums properly up the WBS, and next to it you get Planned Value Labor Units and Schedule Performance Index (Labor Units), all calculated without a cent of cost. Divide earned hours by baseline hours at any WBS level and you have the figure the client asked for.
An earned value analysis example in hours
One WBS node, three activities, 2,000 baseline hours. These are illustration numbers, chosen so the arithmetic is easy to follow:
- Formwork, 400 baseline hours. The crew has booked 380, estimates 220 still to go, and the site engineer assesses it at 50% physically complete.
- Rebar, 600 baseline hours. 240 booked, 360 remaining, 40% complete.
- MEP first fix, 1,000 baseline hours. Not started.
Units % Complete at the node is actual over at completion. That's 620 booked hours over 2,200 at completion hours (600 + 600 + 1,000), which is 28.2%.
Earned hours are baseline hours times percent complete: 200 for formwork, 240 for rebar, nothing for MEP. 440 earned over 2,000 baseline is 22.0%.
Same schedule. Same data date. Six points apart.
The gap is the formwork overrun. Units % Complete rewarded the crew for every extra hour they booked. Earned hours credited them with half the formwork, because half the formwork is what is standing on site.
Earned hours also give you the two ratios a cost loaded schedule would have given you. Say the baseline planned 700 hours by this data date: formwork finished, rebar half done. SPI in hours is 440 / 700, or 0.63. And earned over actual, 440 / 620, comes out at 0.71, meaning each booked hour is producing about 0.71 hours of planned work. That second ratio is the productivity question every site manager actually cares about, and Units % Complete hides it completely.
When each number wins
I'm not saying Units % Complete is useless. It answers a different question, and it answers it well.
Use it when the question is budget burn. How many hours have we consumed against what we now expect to spend? That feeds the hours forecast, and it's the number the commercial team should be watching.
Use earned hours for anything with the word progress on it. The client report, the S-curve against baseline, the SPI, the monthly narrative. Progress means work in place, and only earned hours measures that.
My view, and plenty of planners will disagree: Units % Complete should never be the headline figure on a progress report. It rises when things go badly. A metric that improves as productivity falls has no business on page one.
One caveat bites earned hours too. Earned hours are only as honest as the percent complete underneath them. If an activity's % Complete Type is Duration, its percent is time elapsed, and earned hours inherit that. If it's Units, its percent is hours spent, and you're back to measuring burn through the side door. For anything a crew physically installs, set complete_pct_type to Physical and have someone who walked the area enter the number.
Getting the number out, in P6 or Excel
In P6, open Project, Assign Baselines before anything else. Every earned value column reads the baseline, not the current budget, so make sure it's the one the client accepted. Like the setting that decides which calendar a lag uses in P6, it is a project level choice that travels with the file and never shows on the Gantt.
Then build an Activities layout grouped by WBS with Earned Value Labor Units, Planned Value Labor Units and the baseline's budgeted labour units. The bands sum the earned and planned hours for you. The percentage needs one division the bands won't do, so export the layout.
In Excel it's two SUMIFS per WBS row: earned hours under that node, divided by baseline hours under that node. If your WBS codes are laid out as a path, a wildcard on the parent code catches every child. It's the same export I use to review a monthly schedule update in Excel, so if you already do that, the columns are sitting there.
Tip: Some planners give every labour resource a Price / Unit of 1, so cost equals hours and Performance % Complete rolls up by itself. It works, with two catches. Existing assignments only pick up the new price after Tools, Recalculate Assignment Costs. And because earned value reads the baseline, a baseline saved before the prices went in still says zero. If you can't re-baseline, that route is closed.
Cost loading arrives on most jobs eventually. When it does, Performance % Complete will start working at the top of the WBS, and it should land close to your earned hours figure as long as labour drives most of the cost. If the two disagree badly, look at where the material and plant money was loaded. It usually sits on a handful of activities, and those activities are now steering your progress figure.